A supplier quotes your temperature controller for a 200-board pilot run. Before you issue the purchase order, engineering approves a different connector and purchasing increases the order to 500 boards. The bare PCB is still at the same revision. Is the original assembly quote still valid?

Request a revised PCB assembly quote when a change could affect price, availability, lead time, or build scope. If a change is administrative, ask the supplier to confirm in writing that the existing quote still applies. At XWONDER, we recommend starting with a list of the assumptions behind the original quote, recording each change, and checking the supplier's reply against the PO before release.

What Was the Original PCB Assembly Quote Based On?

PCBA quote revision control starts with the supplier's issued quotation and the file list it references. Track the quote revision, the RFQ package revision, and the individual engineering file revisions separately. A quote may reference an RFQ package containing several file revisions. The approvals and references establish which files apply to the build.

Quote Assumptions Checklist

  • Quote record. Quote ID, revision, issue date, validity, and whether the quote is budgetary, conditional, or ready for order placement.
  • Build definition. Assembly part number and variant, assembly revision, BOM revision, bare PCB revision, and the file index for drawings and placement data.
  • Order basis. Quantity per release, applicable price tier, supplier- or customer-supplied material, and any alternate parts assumed in the offer.
  • Work included. Programming and test procedure revisions, fixture responsibility, included operations, and exclusions.
  • Delivery and open conditions. Lead-time start event, delivery commitments, and assumptions about part availability or approvals.

Record each item as confirmed, assumed, or open. If the quote omits a revision or responsibility, ask the supplier to identify the basis it used. Our PCB assembly RFQ checklist covers how to assemble the original file package.

Which Changes Require a Revised PCB Assembly Quote?

Use the table to choose the response you need. A written confirmation can close an administrative change. A limited quote update can work for a clearly bounded change when the supplier explicitly confirms the rest of the original offer still applies. Ask for a replacement quote when several changes interact or the original basis is unclear.

Change Decision Table for Buyers

What changed?What should you request?What should the supplier confirm?
File name or drawing note correctedWritten confirmation if engineering verifies the build requirements are identical.The corrected file and the quote revision that still applies.
BOM part number or approved alternateImpact review. Ask for a limited update or replacement quote based on the impact.Quoted part, substitution approval, availability, and any assembly or test changes.
PCB fabrication or assembly requirementRequote the affected scope. Request a replacement quote if several operations change.Applicable files, updated scope, and impact on price and delivery.
Order quantity, release schedule, or supply responsibilityRefresh the affected terms. Ask for a replacement quote if the changes affect multiple commitments.Valid price tier, lot size, material ownership, and lead-time basis.
Test, firmware, or fixture requirementRequest an update for the affected work.Procedure revision, test coverage, fixture responsibility, and timing.
Quote validity expiredRequest a validity refresh.Current price, available material, lead time, and a new expiry date.
Material committed or boards already in processRequest a written impact assessment. Review any revised terms before agreeing to the change.Existing material disposition, affected fees or schedule, and the first lot to use the revised build.

For test changes, reference the exact operation and procedure revision. A change from sample testing to testing every board can affect the quote even when the BOM stays the same. Our PCBA inspection and test comparison explains the different checks you may need to specify.

PCB assembly quote revision workflow showing the original quotation and engineering change record, followed by supplier confirmation and purchase order verification.
Use the original quotation and the change record to decide what the supplier must confirm before you release the PO.

What Should You Send With a Requote Request?

Reference the old quote ID and revision, attach one current file index, and identify the affected build or lot. For each change, record the old value, new value, controlling document, and supplier action. State which assumptions still apply from your side and ask the supplier to confirm them in its response.

Copy this change record format. Change ID | Affected part or operation | Previous value | New value | File or ECO reference | Effective lot | Supplier response needed.

Ask for a specific reply. Confirm the existing quote, issue a limited update that references the prior quote, or issue a replacement quote that identifies what it supersedes.

When you are reviewing offers from several assemblers, issue the same controlled update to each. Compare the replies against the same variant, quantity, test scope, and supply responsibilities. See how to compare PCB assembly suppliers for the broader sourcing decision.

How Do You Carry a Revised Quote Into the Purchase Order?

Illustrative example. The buyer has quote Q-214 Rev 0 for 200 temperature controller boards under RFQ package TC-RFQ-01. Engineering approves a footprint-compatible J3 connector under ECO-017 and releases an updated assembly and BOM. The same bare PCB, placement data, and functional test procedure remain approved. Purchasing changes the first order to 500 units. Both changes apply to the first pilot lot.

Change Record Sent With TC-RFQ-02

ChangePrevious basisReleased updateSupplier action
C01 · J3 connectorJ3-A, BOM Rev 04, assembly Rev BJ3-B, BOM Rev 05, assembly Rev C, per ECO-017Confirm the part quoted, supply availability, and fit with the released assembly and fixture.
C02 · Pilot quantity200 on the first release500 on the first releaseConfirm the 500-unit price and lead time.

The supplier confirms the existing fixture fits J3-B and verifies availability for 500 boards. It issues Q-214 Rev 1 as the replacement for Rev 0. The buyer compares the revised offer with the change record and copies the accepted terms to the PO. The commercial figures below are illustrative.

Old Quote, Replacement Quote, and PO

FieldOld quote · Q-214 Rev 0Replacement · Q-214 Rev 1PO-318 Rev 1
ReferenceTC-RFQ-01TC-RFQ-02. Supersedes Rev 0References Q-214 Rev 1 and TC-RFQ-02
BuildTC-100 assembly Rev B, BOM Rev 04TC-100 assembly Rev C, BOM Rev 05, bare PCB Rev 02TC-100 Rev C, with the TC-RFQ-02 file index attached
Quantity and unit price200 at USD 24.00500 at USD 21.80500 at USD 21.80
Test and fixtureFunctional test procedure Rev 03 for every board, existing fixtureSame procedure and frequency. Fixture fit confirmed. No new fixture chargeIncludes functional test Rev 03 for all 500 boards per Q-214 Rev 1
Lead time and validity15 business days after PO acceptance. Valid through Dec 4, 202620 business days after PO acceptance. Valid through Dec 18, 2026Issued Dec 10 with the revised lead-time basis. Supplier acknowledgment confirms the acceptance date and ship date

By the order date, the original quote has expired and the revised quote remains valid. The buyer releases only the approved version of PO-318 and keeps the superseded quote and earlier PO draft in the project record.

Side-by-side comparison of the original quote, revised PCB assembly quote, and purchase order, with matching build revision, order quantity, and lead-time basis highlighted on the revised quote and purchase order.
The replacement quote and PO should reference the same released build, quantity, and lead-time basis.

What Should Match Before You Release the Purchase Order?

  1. Engineering confirms the build. Verify the assembly revision, RFQ package, deviations, and the first lot affected by the change.
  2. Purchasing confirms the offer. Check the quote revision and validity, price and quantity, one-time charges, exclusions, and delivery terms. If two documents disagree, obtain a written resolution before releasing the PO.
  3. The supplier acknowledges the order. Check that the acknowledgment references the correct PO and build, and confirms the ship date or the agreed event that starts lead time. If material was already committed, keep the agreed disposition and lot cutover with the order record.

What Else Should Buyers Confirm About Quote Revisions?

Does Every BOM Revision Require a New Quote?

A clerical correction may only need written confirmation. Ask for an impact review when a part, approved alternate, source, or quantity per assembly changes.

Is an Approved ECO Enough to Update a Quote?

An ECO authorizes the engineering change. Obtain the supplier's separate confirmation of revised price, scope, availability, and timing where applicable.

Can a Supplier Update One Quote Line?

Yes, if its written update identifies the original quote, the line being replaced, the effective scope, and the terms that still apply. Link the two documents in the order record.

Which PCBA Projects Can You Discuss With XWONDER?

Do You Need a Revised PCBA Quote?

Send XWONDER the previous quote reference, current file index, and a short description of the changes. Include the expected quantity and tell us which price, delivery, or build assumptions you need confirmed.